Taking Delivery, Unpacking And Checking - ABB REL670 Installation And Commissioning Manual

Line distance protection ied
Hide thumbs Also See for REL670:
Table of Contents

Advertisement

1
12

Taking delivery, unpacking and checking

Taking delivery, unpacking and checking
Procedure
1.
Remove the transport casing.
2.
Visually inspect the IED.
3.
Check that all items are included in accordance with the delivery
documents.
Once the IED has been started make sure that the software functions or-
dered have been included in the delivery.
4.
Check for transport damages.
If transport damage is discovered appropriate action must be taken
against the latest carrier and the nearest ABB office or representative
should be informed. ABB should be notified immediately if there are any
discrepancies in relation to the delivery documents.
5.
Storage
If the IED is to be stored before installation, this must be done in the orig-
inal transport casing in a dry and dust free place. Observe the environ-
mental requirements stated in the technical data.