IED
142
Control
Information and material for the verification:
•
Protection or control unit, Intelligent electronic device (IED), configured and
with settings entered.
•
Configuration diagram for the IED
•
Terminal diagram for the IED, or plant circuit diagram including the IED
•
Technical reference manual for the IED
•
Relay test set for secondary injection
•
Means to indicate, measure and record operation and times, e.g. an event record-
ing facility
•
A bi-stable relay (BR) or two auxiliary relays to simulate a CB
•
Two push-buttons (SC, ST) to operate the BR and a change-over switch (SRY)
to simulate CBREADY
•
Possibly a switch simulation the Synchronism check (SYNC) condition
AR01 - CLOSE CB
Trip
AR01 - CB POS
AR01 - CB READY
Figure 35:
Simulating the CB operation by a bi-stable relay and manual switches
Verifying settings by secondary
BR
SC
ST
SRY
To test
set
en04000202.vsd
Chapter 11
injection
+
-