ABB REL670 Installation And Commissioning Manual page 150

Line distance protection ied
Hide thumbs Also See for REL670:
Table of Contents

Advertisement

IED
142
Control
Information and material for the verification:
Protection or control unit, Intelligent electronic device (IED), configured and
with settings entered.
Configuration diagram for the IED
Terminal diagram for the IED, or plant circuit diagram including the IED
Technical reference manual for the IED
Relay test set for secondary injection
Means to indicate, measure and record operation and times, e.g. an event record-
ing facility
A bi-stable relay (BR) or two auxiliary relays to simulate a CB
Two push-buttons (SC, ST) to operate the BR and a change-over switch (SRY)
to simulate CBREADY
Possibly a switch simulation the Synchronism check (SYNC) condition
AR01 - CLOSE CB
Trip
AR01 - CB POS
AR01 - CB READY
Figure 35:
Simulating the CB operation by a bi-stable relay and manual switches
Verifying settings by secondary
BR
SC
ST
SRY
To test
set
en04000202.vsd
Chapter 11
injection
+
-