8.3.2
Frequency protection
Extended testing
Procedure
1.
The test above can be repeated to check a positive setting of Start-
FreqGrad .
2.
The tests above can be repeated to check the time to reset.
3.
The tests above can be repeated to test the RESTORE signal, when
the frequency recovers from a low value.
Completing the test
Continue to test another function or end the test by changing the test mode setting to off. Restore