1. Introduction
8
1.4.2.

Equipment categories

Gas category Gas type
II
Natural gas H (G20) 20
2ESi3P
Natural gas L (G25) 25
Propane (G31)
The boiler is preset in the factory to operate on natural gas H (G20).
¼ For operation on another type of gas, see chapter: "Adapting
to another gas type", page 65.
1.4.3.

Additional Directives

Apart from the legal provisions and Directives, the additional
Directives described in these instructions must also be observed.
For all provisions and Directives referred to in these instructions, it is
agreed that all addenda or subsequent provisions will apply at the
time of installation.
WARNING
Installation of the appliance must be done by a qualified
engineer in accordance with prevailing local and national
regulations.
1.4.4.

Factory test

Before leaving the factory, each boiler is set for optimum performance
and tested to check the following items:
4 Electrical safety
4 Adjustment (CO
)
2
4 Water tightness
4 Gas tightness
4 Parameter settings
Connection pressure (mbar)
37