5 INSTALLATION
IMPORTANT: first connection
operations must be performed
by a specialised and authorised
technician.
5.1 ELECTRICAL CONNECTION
Check that all switches are in
OFF position before electrically
connecting the machine.
Grounding connection is absolutely
compulsory and the system must
meet the current regulations in the
country of installation.
Check the power supply voltage
(see the indication label); it must
match the voltage of the local grid.
The machine is connected to the mains supply via
the electrical cable. Make sure that the capacity
of the electrical system available is suitable for the
maximum power consumption, indicated on the
coffee machine. Switch in OFF position = 0, switch
in ON position = 1 (in ON position the button lights
up red).
INSTALLATION
ON-OFF
5.2 MAINS / TANK SUPPLY
This operation must be carried out only when the
machine is switched off. Only for the CUBE R
version, it is possible to switch from domestic water
supply to tank or vice versa in the following ways:
Tank
- remove the drain plate;
- use a screwdriver to turn the tap lever to the right
(tank symbol);
- move the SW1 switch lever to the right (tank
symbol);
- refit the drain plate with the rubber pad;
- fill the tank with cold filtered water.
Mains
- remove the drain plate;
- use a screwdriver to turn the tap lever to the left
(tap symbol);
- move the SW1 switch lever to the left (tap symbol);
- remove the rubber pad from the drain plate and
connect the drain pipe with the suitable clamp (see
WATER CONNECTION section).
NOTE: As soon as the machine is turned on, the
display shows the water supply configuration:
"-t-"= from the tank;
"-L-"= from the mains.