03. COMMISSIONING & WELDING
04. FIRST COMMISSIONING
01. Thoroughly clean the machine prior to start up.
02. Make sure that the machine and all electrical cables have no damage.
03. Have specialists verify, whether the machine may be operated using the
available grid supply voltage, and whether it is correctly connected.
04. All safety covers must be mounted.
05. Be sure that the air pressure is min. 6 bar.
02/2021
22
Vetron 5374 HotAir-Welding
1.) In the case of deviations, the machine must NOT be started up!
2.) Connect the machine to a grounded power socket only!