4.1 Service
The system must be checked once every
month by the operator through observati-
on of the switching routine for operational
ability and leaks.
• Close emergency valve or with Komfort:
press test key to carry out functional test
on backwater valve -> valve closes
• Allow water to flow in
• Wait until level-LED + pump trigger.
• Switch off water feed
• Switch off level-LED and wait for pump
• Open hand lever vertical position OPEN)
-> Standard
Komfort: Please note that the backwater
valve must be open after the inspection
has been completed.
The pump should be checked at regular in-
tervals. If operational noises increase,
pumping capacity decreases or there are
vibrations in the pipeline system, the pump
housing and impeller must be checked for
any stubborn soiling or wear.
4.2 Maintenance (at least every six
months)
CAUTION: Disconnect the unit from the
mains during all servicing work! Heed
safety instructions! No warranty will be
granted in the event of insufficient
maintenance! All the servicing and
maintenance work described below
may only be carried out by authorised
qualified personnel. Repairs may only
be carried out by the manufacturer.
DIN 1986, part 3, must be heeded during
maintenance work on systems. Maintenan-
ce work must be carried out at least every
six months by authorised qualified staff.
The following tasks have to be carried out:
• Visual inspection of the complete system
• Thorough cleaning of the complete sy-
stem and the pump
• Check on the complete system and pump
housing for external damage and visible
wear
• Check on the pump for free movement,
wear and deposits
• Check the connection cables for mechani-
cal damage and wear
• Check the seal connections for leaks and
any recognisable wear
• Insulation test on the pump motor
• Check the control unit for damage and
soiling
• Check and clean the ventilation valve
• Clean the optical probe
4. Service and maintenance
Standard
a) Pull the insertable part out
b) Clean all the parts
c) Check the seals
d) Apply lubricant (e.g. fittings grease)
to the outside of the seals of the ins-
ertable parts as well as the guide
parts of the flap valves
We recommend these jobs after longer peri-
ods of standstill or intermediate storage, too,
as well as after longer or frequent occurren-
ces of backwater. If problems should occur
that cannot be eliminated, please contact
the specialist company who carried out the
installation (see stamp on cover sheet) if in
doubt.
4.2.1 Mounting the two covers (see Fig.
12, 13, 14)
Insert the covers on one side, push the other
side down and lock in place using the locking
levers. During installation of the overflow
cover the red flap lever or the motor flap po-
sition must always be "CLOSED"
4.3 Test
4.3.1 Test Standard
1. Hold the pump probe into the water "On" level
4.3.2 Test Comfort
1. Hold the motor probe into the water Flap closes
2. Hold the pump probe into the water Pump starts
22
Comfort
e) Insert the insertable part exactly
f) Make sure the attachment clips are in
place properly!
g) Heed cover installation 4.2.1
h) Carry out functional test in accordan-
ce with instruction manual 010-846.
Abb. 12
Level-LED lit
Pump starts
Pump-LED lit
Backwater-LED flashes
Flap-LED flashes
Flap closed
Backwater-LED flashes
Flap-LED lit
Pump-LED lit

Advertisement

Table of Contents
loading

This manual is also suitable for:

Pumpfix f comfort

Table of Contents