Standard and pocketed slide doors
Hide thumbs Also See for GT1175:
Table of Contents

Advertisement

www.NabcoEntrances.com
Rev.11-12-20
2. Install the Bottom Guide by sliding rollers into the Bottom Rail so the Bracket sticks out from underneath (in direction of
where the Slide door is to be installed).
3. Use the Bracket to slide the Bottom Guide towards the Pivot Stile. Replace the Cover Plate.
Bo om Guide Assembly
DN 0865
SECTION 13 .3: Install the Floor Bracket
1. Snap a chalk line between Jamb Tubes in front of Sidelite Panel.
Jamb Tube
DN 0624
2. Go to the bottom of the Strike Stile. Insert the Floor Bracket inside the Bottom Rail so the bottom plate portion sticks out
from underneath (in direction of where the Slide door is to be installed).
3. Close the Slide Door. Adjust the Fixed Panel for weathering gap. Adjust the Slide Door for racking and plumb to Strike Jamb.
4. Secure the upper plate portion of the Floor Bracket to the side of Strike Stile with (1) 1/4-20 x 1/2 inch Phillips Head screw.
5. Use the Floor Bracket as a template to drill (2) screw holes for #14 x 1-1/4 inch Flathead Tapcon screws.
6. Secure the Floor Bracket to the floor with (2) #14 x 1-1/4 inch Flathead Tapcon screws. Replace the Cover Plate.
Bo om Rail
Strike S le
Floor
Bracket
DN 0864
CHAPTER 14: INSTALL THE SLIDE DOOR
Attention:  No matter the configuration, the Fixed Sidelite is installed the same way .
GT1175StandardandPocketedSlideDoorsInstallationManual;withOpusController
Floor
Fixed Panel
1/4-20x1/2"
Screw
An -Rise Roller
Hanger Roller
Nut
DN 1043
Figure 50 Slide Bottom Guide into Bottom Rail
Jamb Tube
Chalk Line
Figure 51 Ensure Fixed Panel is Square
1/4x1-1/4"
Tapcon Screw
Figure 52 Install Bottom Bracket
Carrier
P/NC-00370
Bo om Rail
Figure 53 Carrier with Rollers