Installation on collective flues in positive pressure (fig 18)
The collective flue is a flue gas exhaust system suitable for collecting and expelling the
combustion products of several appliances installed on several floors of a building.
The positive pressure collective flues can only be used for type C condensing appliances.
Therefore the B53P/B23P configuration is forbidden. The installation of boilers under
collective pressure flues is allowed exclusively in G20.
The boiler is sized to operate correctly up to a maximum internal pressure of the flue no
higher than the value of 25 Pa. Check that the fan speed corresponds to what is shown in
the table "technical data".
Make sure that the air intake and exhaust pipes of the combustion products are watertight.
WARNINGS:
b
The appliances connected to a collective pipe must all be of the same type and have
equivalent combustion characteristics.
b
The number of devices connected to a positive pressure collective pipe is defined
by the flue designer.
The boiler is designed to be connected to a collective flue sized to operate in conditions
where the static pressure of the collective flue pipe can exceed the static pressure of the
collective air duct of 25 Pa in the condition in which n-1 boilers work at maximum rated heat
input and 1 boiler at the minimum rated heat input allowed by the controls.
b
The minimum permissible pressure difference between the flue gas outlet and the
combustion air inlet is -200 Pa (including - 100 Pa of wind pressure).
For both types of exhaust, further accessories are available (curves, extensions, terminals,
etc.) which make possible the flue gas exhaust configurations foreseen in the boiler booklet.
b
The pipes must be installed in such a way as to avoid condensation sticking which
would prevent the correct evacuation of the combustion products.
b
A data plate must be present at the connection point with the collective flue pipe. The
plate must include at least the following information:
- the collective flue is sized for boilers C(10) type
- the maximum permissible mass flow of the combustion products in kg/h
- the dimensions of the connection to the common pipes
- a warning concerning the openings for the air outlet and the entry of the combu-
stion products of the collective pressure pipe; these openings must be closed
and their tightness must be checked when the boiler is disconnected
- the name of the manufacturer of the collective smoke pipe or its identification
symbol.
b
See applicable legislation for the discharge of the combustion products as well as
local regulations.
b
The flue gas pipe must be suitably selected based on the parameters shown below.
maximum length
ø 60-100
4,5
ø 80
4,5
ø 80/125
4,5
b
The terminal of the collective pipe must generate an upward air current.
b
Before attempting any operation, disconnect the appliance from the electrical supply.
b
Before assembling, lubricate the gaskets with a non-corrosive glide lubricant.
b
The flue gases discharge pipe should be inclined, if the pipe is horizontal, by 3°
towards the boiler.
b
The number and characteristics of the exhaust ventilation devices which are the real
characteristics of the flue itself.
b
The condensation can flow inside the boiler.
b
The maximum recirculated value allowed in wind conditions is 10%.
b
The maximum permissible pressure difference (25 Pa) between the combustion
products inlet and the air outlet of a collective flue can not be exceeded when-
1 boiler work at the maximum nominal heat output and 1 boiler within minimum
temperature allowed by the checks.
b
The collective smoke pipe must be adequate for an overpressure of at least 200 Pa.
b
The collective flue must not be equipped with a wind-proofing device.
At this point it is possible to install the curves and extensions, available as accessories,
depending on the type of installation desired.
The maximum permissible lengths of the flue pipe and the air intake pipe are given in the
instruction manual of the reference device (fig 18a-18b).
With C(10) installation, in any case, report the number of fan speed (rpm) on the
label placed next to the data plate.
Installation currently not available on model 40kW.
8
minimum length
UM
0,5
m
0,5
m
0,5
m
3.15
Filling the heating system and eliminating air
Note: When the air is being eliminated from the boiler using the deaeration tap (A - fig.
19) the filling of the siphon occurs ("3.18 Condensate siphon"); make very sure that the
level does not exceed the level shown in the figure, if necessary closing the deaeration tap
(A - fig. 19).
Note: the first filling operation must be carried out by turning the filling tap (B - fig. 19) with
the boiler OFF.
Note: each time the boiler is powered up, the automatic venting cycle is carried out.
Note: the presence of a water alarm (40, 41 or 42) does not allow the venting cycle to be
carried out. The presence of a domestic hot water request during the venting cycle interrupts
the venting cycle.
Once the hydraulic connections have been made, fill the heating system as follows:
- Set the boiler to OFF by pressing button 1
- Slowly open the de-aeration tap (A - fig. 19) and the system filling tap (B - fig. 19)
- After about 1 minute, close the de-aeration tap (A - fig. 19)
- Wait for the pressure to increase: check that it reaches 1-1.5 bar; then close the system
filling tap (B - fig. 19).
Note: if the mains pressure is less than 1 bar, keep the system filling tap (B - fig. 19) open
during the venting cycle and close it once it has finished.
- To start the vent cycle shut off the electrical power for a few seconds; connect the power
again leaving the boiler OFF. Check that the gas tap is closed.
- At the end of the cycle, if the circuit pressure has dropped, open the filling tap (B - fig. 19)
again to bring the pressure back up to recommended levels (1-1.5 bar)
The boiler is ready after the vent cycle.
- Remove any air in the domestic system (radiators, zone manifolds, etc.) using the bleed
valves.
- Once again check that the system pressure is correct (ideally 1-1.5bar) and restore the
levels if necessary.
- If air is noticed when operating, repeat the vent cycle.
- Once the operations are finished, open the gas tap and ignite the boiler.
At this point it is possible to carry out any heat request.
3.16
Draining the heating system
Before draining, set the boiler to OFF and shut off the electrical supply setting the system's
main switch to "off".
- Close the heating system's taps (if present).
- Open the de-aeration tap (A - fig. 19)
- Connect a pipe to the system discharge valve (C - fig. 19), then manually loosen it to let
the water flow out.
- Once the operations are finished, remove the pipe from the system discharge valve and
close the system discharge (C - fig. 19) and de-aeration (A - fig. 19) taps again.
3.17
Emptying the domestic hot water circuit
Whenever there is risk of frost, the domestic hot water system must be emptied in the
following way:
- turn off the main water supply tap
- turn on all the hot and cold water taps
- drain the lowest points.
3.18

Condensate siphon

When the boiler is first started the siphon for collecting the condensate is empty.
When eliminating air from the boiler, the siphon fills.
- Slowly open the de-aeration tap (A - fig. 19) and leave it open until the amount of water
contained in the siphon reaches the ledge.
- Close the de-aeration tap (A- fig. 19)
- Check that there are no leaks from the SRD device connection zone and that the device
allows the liquid to run off correctly.
- Check that the system pressure has not dropped below 1 bar. If necessary, fill the system.
Repeat this operation during maintenance work.
CHECK THAT THE CONDENSATE DRAIN OUTLET SIPHON CONTAINS WATER, IF IT
WAS NOT FILLED PROCEED AS DESCRIBED ABOVE.

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Mynute x 25 cMynute x 30 c

Table of Contents