Finalizing the Installation

1. Remove the glass (see page 41).
NOTE:
If using propane (LP) convert the appliance prior to installing the media.
2. We recommend you purge the gas line at this time (with the glass removed). This allows gas to be detected
once it enters the firebox, ensuring gas does not build up.
3. Install the batteries into the battery holder
4. Turn on gas to the heater. Leak test all gas joints prior to starting the appliance. Start the pilot to verify gas
supply (see instructions on page 40). Leak test all the gas joints. Turn the gas control knob to "OFF" to shut
off the appliance.

Pilot Flame Inspection

The pilot flame should look like the illustration below. Adjust the pilot flame if necessary.
The pilot flame should look like the illustration below. Adjust
the pilot flame if necessary.
To adjust the pilot flame, turn this screw. Clockwise lowers
the flame while counter-clockwise raises it
5. Replace the glass.
6. Start the main burner and verify the burner ignites correctly.
7. Leak test all gas joints.
© Travis Industries
Installation
(for qualified installers only)
11/9/20 - 1503
The pilot flame should touch the top 3/8" of the
sensing electrode and make contact with the pilot
hood. Adjust the pilot up or down as necessary.
Sensing
electrode
Pilot Hood
Spark
Electrode
PB36 CF Install (Aust)