NetCol8000-A013 In-room Air Cooled Smart Cooling
Product
User Manual (600 mm Width)
Table 4-5 Communication settings
Item
Baud Rate
Comm Address
Enable Monitoring
Resistor
----End

4.6 Commissioning Procedure

Context
● The outdoor unit has been charged R410A refrigerant for 5 kg before delivery.
The indoor unit has been charged no refrigerant.
● If the R410A refrigerant is provided by Huawei, put the refrigerant cylinder
upside down when charging the refrigerant. If the refrigerant is not provided by
Huawei, check with the refrigerant provider whether the cylinder has a siphon.
If the cylinder has a siphon, stand the cylinder when charging refrigerant. If the
cylinder has no siphon, put the cylinder upside down when charging refrigerant.
These measures ensure that the refrigerant is charged in the liquid state.
Procedure
Step 1 Tap
Issue 02 (2020-11-09)
Remove the refrigerant steel cylinder after confirming that sufficient
refrigerant has been injected.
If no electric heater or humidifier is configured, skip the commissioning
procedures for such components.
NO TICE
to start the smart cooling product.
Copyright © Huawei Technologies Co., Ltd.
Description
Set the baud rate as
required. The value
should be consistent
with that set on the
NMS.
The communications
address in one RS485
NMS must be unique,
which is irrelevant to the
cable connection
sequence or teamwork
address.
In an NMS, the values
for the first and last
smart cooling products
by cable routing are
"Yes".
4 Power-On Commissioning
Default Value
9600
1
No
73