Preparation of the machine
Check:
• the machine for any damages.
• for transport damage to the paint.
• hydraulic hoses for cuts and other damage. Check that none of the other hydraulics components
were damages during transport.
• that the frame has not been damaged.
• that the transport wheels are secure and in good condition.
• air pressure level according to technical specifications.
• that all wearing points are intact.
• that all distance clips for depth adjustment are included.
• that all light systems are in working order (if any such system is mounted).
Check the torque:
• wheel bolts 386 NM
• 6 pcs bolts 541 NM
Check machine functioning (tractor needed):
• raising – lowering – hydraulic unfolding
• spindle adjustable levelling discs / levelling tines
• spindle adjustable support wheels
Triple-Tiller Airy 2,5m – 4m