Generac Power Systems PowerPact 6561 Installation Notes page 43

Air-cooled generator
Table of Contents

Advertisement

Control Wires
Control wires between the switch and the generator consist of:
Utility voltage sensing wires N1 and N2,
Operating control wires #23,and 15B or 194 and 0,
And don't forget T1 120VAC for the Battery charger.
GenReady
Connect N1 and N2 to the 15A 2 pole breaker provided in the top of the load center (switch).
Connect wires 23 to Transfer, 15B or 194 to 12VDC+ and 0 to 12VDC - on the green block on the side
of the transfer switch operator.
The transfer switch operator requires a 5A fuse (supplied) in the +12Vdc for operation.
It will be necessary to install the 5A fuse in the 12Vdc supply line before it leaves the generator.
Wire T1 (battery charger) from the generator will go to the bottom right 15A Duplex Breaker (Not
Supplied) to be installed on the Generator-fed load circuit breakers.
Control circuit wire must run in a separate conduit, unless the length is 30 feet or less.
All control wires must be a minimum 300Vac rating and #14 AWG size. (Generac Control & Install
Cables are #18 AWG 600Vac rated)
THHN wire is recommended. Do not use Thermostat wire.
RTSY/T/W, RTSR/P/C, RTSB, RTSI, RTJ
The Control wires are routed to the Fuse block and connection block next to the Main Breaker.
On the Fuse Block N1 and N2 (Utility) are the Yellow N1 and N2 sensing wires.
T1 (Load) is for Blue T1 battery charger wire.
On the small Block, White 23 Transfer is for the white 23 wire for transfer signal control.
Red 194 +12VDC is for the Red 15B or 194 +12VDC for the transfer relay.
Black 0 DC Common is for the black 0 wire common ground.
RTG – Prewired
The Control Wires are prewired on the RTG Switches from the 30' whip.
require a 0 wire.
Circuit Breakers RTG-EZ Switch & RTSR/I Sub-Panel
Note: Some local codes may require splices to be in a separate junction box not in the main panel box.
Turn off the main breaker on the distribution panel before running any wires into the panel box.
Balance must be maintained when moving circuit locations from the main panel box to the emergency
load center.
Circuit breaker positions alternate buss bars vertically.
Circuits sharing a neutral wire should be either moved together or NOT moved.
Circuits to be removed must be protected by the same size breaker. For example, 15A to 15A, 20A to
20A. (RTG is all #12 wire so you can swap out the breakers)
In the main panel box, remove the black wire (hot) from the circuit breaker of the circuit to be
protected in the event of a power failure.
Connect it to the matching lead from the circuit breaker in the load center of the transfer switch.
All circuit wires in the transfer switch load center are color-coded and labeled for easy identification.
Trace each black (hot) wire connected and remove the corresponding white wire from the neutral
block in the main panel (from the same Romex cable).
Connect the white wire to the matching circuit number on the white (neutral) wire from the
emergency load center.
Repeat this process for the remaining circuits to be transferred to the transfer switch load center.
Use the same procedure for the RTSR/P/C Sub-Panel except it will not be prewired in the Sub-Panel.
Note: RTG switches do not
43

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the PowerPact 6561 and is the answer not in the manual?

Questions and answers

Table of Contents