6. Operation

6.1

Preparation for Starting Operation

NOTE
• Mount the XS110A before using the product. Refer to 4.2.1 "Mounting
with XS110A" for mounting method of XS110A.
• Check that the process pressure take-out valve (main valve), the drain
valve and the stop valve of the hand valve are closed.
(1) Confirmation of installation
This product is correct according to the contents of Chapter 4 "mounting"
and Chapter 5 "piping of the conducting pipe". Make sure it is attached.
(2) Check for connection leakage
Introduce the process fluid into the conduit and XS530 as follows:
 Open the main valve and introduce the process fluid into the manifold.
 Gradually open the hand valve and introduce the process fluid into the
pressure receiving portion of the XS530.
 Check that there is no pressure leak in the pipe, XS530, etc.
(3) Checking the Firmware
Make sure the Sushi Sensor has the latest firmware. For details on how to
check and update the firmware, refer to "IM01W06C01-01EN".