Agilent Technologies 280-DS Operator's Manual page 75

Mechanical qualification system
Table of Contents

Advertisement

4
Operating the 280-DS
Test Completion
1 Upon completion of the test sequence:
Figure 53.
2 Click Complete to update the physical parameters and display the Method
280-DS Operator's Manual
• If the method has the Update Qualification Record option selected
("Update Qualification Record"
passed the specification, you can specify the next qualification due date.
• If any of the tests failed, then the dissolution apparatus is marked Out of
Calibration and the old calibration due date cannot be updated.
• If Update Qualification Record is not selected then the old qualification due
date remains and will be displayed for reference only.
Test Completion Screen - Successful
Completion screen. When the test is complete, the report is compiled and
displayed on screen. See "Test Reports" on page 82..
on page 38) and all of the parameters have
75

Advertisement

Table of Contents
loading

This manual is also suitable for:

G7980aa

Table of Contents