Precautions When Connecting The Electrical Wiring - Daikin Altherma 3 R F Installer's Reference Manual

Hide thumbs Also See for Altherma 3 R F:
Table of Contents

Advertisement

9
|
Electrical installation

9.1.1 Precautions when connecting the electrical wiring

Installer reference guide
104
Typical workflow
Connecting the electrical wiring typically consists of the following stages:
1
Making sure the power supply system complies with the electrical
specifications of the heat pump.
2
Connecting the electrical wiring to the outdoor unit.
3
Connecting the electrical wiring to the indoor unit.
4
Connecting the main power supply.
5
Connecting the backup heater power supply.
6
Connecting the shut-off valves.
7
Connecting the electrical meters.
8
Connecting the domestic hot water pump.
9
Connecting the alarm output.
10
Connecting the space cooling/heating ON/OFF output.
11
Connecting the changeover to an external heat source.
12
Connecting the power consumption digital inputs.
13
Connecting the safety thermostat.
DANGER: RISK OF ELECTROCUTION
WARNING
ALWAYS use multicore cable for power supply cables.
INFORMATION
Also read the precautions and requirements in the
4
precautions" [
WARNING
All wiring MUST be performed by an authorised electrician and MUST comply
with the applicable legislation.
Make electrical connections to the fixed wiring.
All components procured on-site and all electrical construction MUST comply
with the applicable legislation.
 9].
"2  General safety
ERGA04~08EAV3(A) + EHVH04+08SU18+23EA6V
Daikin Altherma 3 R F
4P629090-1 – 2020.08