Installation
Figure 24: Raised Floor Anchor
1. If necessary, remove the tiles.
2. Insert the anchor assembly, including the threaded rod, into the hole flush against the floor.
3. Finger-tighten the torque nut. This step will set the cone nut into the anchor.
4. Preload the anchor by tightening the torque nut 1 1/2 turns. (Do not exceed 50ft lbs)
5. Remove the torque nut and remove the anchor rod via the 1/4" protrusion at the top of the rod.
6. Insert 1,000 mm threaded rod into hole and make sure that rod has threaded onto the set anchor.
7. If earthquake bracing is required, perform
continuing with this procedure.
Note: Bracing is required in earthquake zones 3 and 4 when installing a cabinet onto a raised floor
with a spacing of 1.5 feet or more between the raised floor and the subfloor.
8. Lay the isolator pad on the floor with the holes in the isolator pad aligned over the anchor assemblies.
9. Roll the cabinet (still on the dolly) into position over the isolator pad.
Topple: Two people are needed to position the cabinet onto threaded rods.
910-5681-001 Revision E, February 2014
Procedure
Raised Floor Earthquake Bracing
Cabinet Installation