Installation

Overview

This chapter describes how to unpack the application cabinet from the crate, prepare a concrete or
raised floor for installation, anchor the frame to floor and overhead rack, examine the grounding
requirements and the cabling.

Unpacking the Cabinet

This section describes the steps to unpack the cabinet. Each cabinet is shipped in a wooden crate on
a shock pallet. See

Figure 17: Packed Cabinet Crate

Required Tools

• 9/16" Open End Wrench
• 9/16" Socket with Drive Ratchet
• 15/16" Socket with 1/2" Drive Ratchet
• 15/16" Open End Wrench
• 10 mm Allen Wrench
• 19 mm Socket with Drive Ratchet
910-5681-001 Revision E, February 2014
Figure 17: Packed Cabinet