5. S-Box Installation and Connection
• Precautions for installing S-Box
① Installing it in a 19-inch server rack is recommended.
※ When connecting two or more sets for Multi-link HDR, install them in the six-sided shield rack. (Only SBB-SNOWJMU)
②
Make sure the air vent is open and not overturned or turned sideways.
③
Exercise caution to ensure that the air vent is not covered by an object. Covered air vent may cause overheating of
the product.
④
If installing multiple S-Boxes, make sure there is a gap of at least 1U (44.45 mm) from the product at the top.
⑤
If installing an S-Box onto a wall, make sure there is a gap of at least 10 mm between the wall and the top, bottom
and sides of the product. Make sure there is a gap of at least 50 mm between the cable ports and the wall to ensure
proper cable connection.
⑥
Maintain the residual heat inside the rack at a temperature below 35°C.
⑦
Exercise caution to ensure that no liquid enters the air vent of the product.
Samsung Electronics
34