INSTALLATION
2.2 Installation
The top of the SMILE-T10 should be at least 300 mm from the ceiling or structure above
the SMILE-T10, the ceiling or structure surface shall be suitably non-combustible for an
area of 600 mm past the extremities of the SMILE-T10.
Where more than 4 batteries are installed, some batteries shall be installed by the side,
distance between two rows of batteries shall be not less than 100 mm
SMILE-T10 shall be mounted with the highest point no greater than 2.2 m above the
floor or platform.
Figure 11 Unpacking the Battery
Step 1 Take out the battery from the packaging box.
NOTE: the packaging box must be placed in accordance with the marked direction, the
upward carton, unpacking in the other direction is wrong.
Figure 12 Removing Front Panel
Step 2 Pull the buckle from the bottom right in the middle and pull the top two guide rods
to remove the front panel.
11
12
Step 3
Use a screwdriver to assemble the battery mounting bracket on the outside of the battery,
as Figure 13 shows.
Step 4
Confirm the installation place at first.
Push the battery against the wall and confirm the location of the battery with a horizontal ruler.
Pack the PE bag on the battery to block out the dust before drilling.
Please drill four holes (two on each side) directly on the wall at the marking positions of the
brackets with an impact drill (bit φ 8.0mm, length 20cm), and the depth of each hole is about 7 cm.
Figure 13 Assembling Battery Brackets