Step 8 Please connect one DC power cable from INV+ port on HV50056 to BAT+ port
on SMILE-T10-INV, and another DC power cable from INV- port on HV50056 to BAT-
port on SMILE-T10-INV. The AC auxiliary power cables which have been prewired onto
the inverter, shall be connected to the AC auxiliary port on HV50056, as shown in
Figure 27.
Figure 28 Connection of the Communication Cables on the Inverter
Side-Removing Waterproff Baffle
Step 9 Please remove the waterproof baffle of the inverter at first as shown in Figure 28.
Figure 29 Connection of the Communication Cables on theInverter Side
Step 10
Please pass the cable through the waterproof cap, the sealing ring and the joint on the
baffle and then connect with an RJ45 connector, see Figure 29.
Figure 30 Network Cable Type B
NOTE: The communication cable is in type B, see Figure 30.
19
20
FFigure 31 Connection of the Communication Cables on the Inverter Side
Step 11
Connect the communication cable between INV COM port of HV50056 and EMS COM port
of the Inverter, as Figure 31 shows.
Step 12
Fix the waterproof baffle back to the inverter and fix the waterproof cap.
NOTE: For indoor user, Step 18 and 20 are not needed. After removing the waterproof
baffle, please connect INV COM port of HV50056 and EMS COM port of the Inverter
with a regular 568B network cable.
Step 13
Connect the PV MC4 connector to the PV ports of the inverter.
Figure 32 Connection of PV cables