This chapter describes what you have to do and know on-site to install the system.
Typical workflow
Installation typically consists of the following stages:
1
Mounting the outdoor unit.
2
Mounting the indoor unit.
3
Connecting the refrigerant piping.
4
Checking the refrigerant piping.
5
Charging refrigerant.
6
Connecting the water piping.
7
Connecting the electrical wiring.
8
Finishing the outdoor installation.
9
Finishing the indoor installation.
INFORMATION
If you have limited installation space, do the following before installing the unit in its
final position:
remove one or both side panels.
INFORMATION
Depending on the units and/or the installation conditions, it might be necessary to
connect electrical wiring before you can charge refrigerant.
At certain times, you have to open the unit. Example:
When connecting the refrigerant piping
When connecting the electrical wiring
When maintaining or servicing the unit
DANGER: RISK OF ELECTROCUTION
Do NOT leave the unit unattended when the service cover is removed.
DANGER: RISK OF ELECTROCUTION
"7.4.4  To connect the drain hose to the drain" 
ERGA04~08DAV3(A) + EHVH/X04+08S18+23DA/DJ3V+6V+9W7
4
[
  77]. It requires to
Daikin Altherma 3 R F
4P618947-1 – 2020.03

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents