1 Go to [A.4.3]: Commissioning > UFH screed dryout >
Status
2 You can read out the value here: Stopped at + the step
where the underfloor screed dryout was stopped.
3 Modify and restart the execution of the program
(a)
If the UFH screed dryout program was stopped due to a power failure and the power
resumes, the program will automatically restart the last implemented step.
(a)
.