Huawei UPS5000-A-400 kVA User Manual page 83

50 kva, pf 0.9
Hide thumbs Also See for UPS5000-A-400 kVA:
Table of Contents

Advertisement

UPS5000-A-400 kVA
User Manual (50 kVA, PF=0.9)
(1) Battery
cable
Step 3 Route signal cables. First remove the small cover at the bottom of the cabinet, as shown in
Figure
bottom of the cabinet.
Issue 03 (2020-01-10)
Figure 3-41 Routing power cables from the bottom of the cabinet and binding position
(2) Mains input power
cable
3-40. Bind cables to the cabinet.
Copyright © Huawei Technologies Co., Ltd.
(3) Output power
cable
Figure 3-42
shows the signal cables routed from the
3 Installation
(4) Bypass input power
cable
75

Advertisement

Table of Contents
loading

Table of Contents