4.
System parameter settings determine normal UPS operation. Note the following:
Set Single/Parallel after confirmation.
Voltage level refers to the line voltage level. Set it based on the site requirements.
Set Output frequency correctly; otherwise, loads may not work properly.
Issue 03 (2020-01-10)
Figure 5-4 Setting network parameters
After network parameters are set, connect the UPS to the network, ensuring that
maintenance personnel can manage or control the UPS remotely. If remote management
is not required, set the UPS based on the default configurations.
On the System Param. screen, select Single (default value) or Parallel, as shown in
Figure
5-5. Set the voltage level, output frequency, battery capacity, and the number of
batteries, as shown in
Figure
Figure 5-5 Setting system parameters (1)