3: Jniscab-5 Power Outlet And Edco Hsp-121B Installation; Ncb Series Router Power Supply Requirements; Installation Procedure - Johnson Controls Intelligent Fire Integrator ROUTMB Installation & Operation Manual

For johnson control echelon networks
Table of Contents

Advertisement

NCB-IM Routers
NCB-IM Installation
4.4.3 JNISCAB-5 Power Outlet and EDCO HSP-121B Installation

NCB Series Router Power Supply Requirements

This router requires +24VDC @ 0.050A nominal and battery backup in accordance with local code
requirements. It can be powered by any regulated, UL 1481 listed, power limited, battery backed
+24 VDC power source.
NOTE: Each router requires a supervised 115 VAC, 60Hz primary power, regulated, UL 1481 listed,
power limited Uninterruptible Power Supply (UPS).

Installation Procedure

Step 1. Mount a UL50 listed, single gang electrical box in the JNISCAB-5's back box using self
tapping screws provided.
Figure 4.3 Gang Box Installation Diagram
Step 2. Mount the HSP-121 to the box using studs provided.
Figure 4.4 HSP-121 Power Line Protector Installation Diagram