Installation instructions

3.4 Installation

3.4.1 Preparing for the installation

3.4.2 Positioning the machine

Check that there is sufficient room for the machine at the installation location.
Check that correct connections are available for water, electricity, drainage
and possibly steam at the installation location. See TECHNICAL SPECIFI-
CATIONS.
Check that the overheating protection device is reset.
Check the following points before the machine is placed in position:
Check that the fuse for the machine at the site is off, blocked and that out-
going electrical circuits from the machine are non-live.
Remove the protective plastic on the sides which are to be stood against a
wall.
If holes need to be drilled in the machine, the holes must be fitted with an
edge strip or similar protection.
Lift the machine off the pallet by opening the door and lifting internally to-
gether with a counterstay at the back of the machine. The machine should
NOT be lifted by the handle.
Put the machine in position and check that it is horizontal using a spirit lev-
el. Use the legs to adjust the machine height (+ 55mm). Once the machine
has been filled with water, do another check to make sure the machine is
standing level.