9.2.2.2 Installing Batteries for the Extinguishant Control Panel (CE)

Prerequisites
The container has been installed.
Preparations
Tools: protective gloves
Materials: extinguishant control panel batteries
Documents: fire extinguishing device installation position diagram (CE)
Skill requirement: common technician
Procedure
Step 1 Open the door of the fire control box, and install batteries in the reserved position.
Issue 02 (2017-01-10)
Figure 9-11 Operating the electric control head ejector
Remove the protective cover at the electric control head installation position on the
container valve. Align the electric control head and the container valve, and tighten the
electric control head clockwise.
Connect the cables between the electric control head and the extinguishant control panel.
Connect the red wire to the red wire, and connect the black wire to the black wire.
For the diagrams, see the quick installation guide for the solution in use.