FusionModule1000A20 IT Solution
Installation Guide (2016.05, AI Version)
Figure 10-2 Cable layout
----End
10.5.2 (Optional) Routing Cables Through a Buried Pipe
Prerequisites
Preparations
Tools: step ladder, protective gloves, safety helmet
Materials: none
Document: none
Skill requirement: skilled technicians
Operation Method
Route the measured cables through the cable pipe reserved during groundwork, and route the
cables through the feeder windows.
Issue 02 (2017-01-10)
The outdoor area without shelters is free from bad weather condition such as raining,
sandstorm, strong wind, or snowing.
The selected cables have been routed through a pipe (excluding the armored cable).
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
10 Cable Installation Techniques
73