Unpack The 50-100Kva Model Ups - Toshiba 4400 Series Installation And Operation Manual

Battery cabinets
Table of Contents

Advertisement

6.3

Unpack the 50-100kVA Model UPS

The 4400 50-100kVA Battery Cabinet has a C-Channel skid base. The skids are bolted to the shipping
pallet to secure the UPS during shipping. Follow the directions below to unship the 50-100 kVA BAttery
Cabinet.
TOP HEAVY EQUIPMENT. THIS EQUIPMENT WILL TIP OVER EASILY
UNTIL FIXED IN PLACE.
Lift and move carefully, and only with adequate equipment and trained
personnel. IMPROPER LIFTING CAN RESULT IN INJURY OR DEATH.
Carefully inspect the UPS for shipping damage. Units shipped within North America and NAFTA are
shrink wrapped.
1
5. Use a forklift or pallet jack to transport the UPS to
4400 Series UPS Battery Cabinet Installation and Operation Manual – 69445-005
CAUTION
1. Remove shrink wrap.
2. Unbolt the UPS base from the
shipping pallet.
3. Use a forklift to lift the UPS off
the shipping pallet.
4. Put down the UPS and remove
the pallet.
it's installation location. See Section 6.4.
FIGURE 6.2 – UNSHIPPING 50-100KVA BATTERY CABINET
3
4
13