7.3

UPS Anchorage - Standard and Seismic

The 15-30kVA battery cabinet battery cabinet comes with casters and leveling feet. The 50-100kVA battery
cabinet comes with Angle Bracket skids.
The leveling feet allow the 15-30kVA battery cabinets to be rolled into place, then the leveling feet extended
to remove weight from the casters to ensure the battery cabinet remains stationary.
The 50-100kVA battery cabinets can be bolted directly to the floor via the Angle Bracket skids on the base.
Seismic Installations
For additional stability, an optional Seismic Kit is available for each cabinet model (P/N 440300SEISMICKIT
for the 15-30kVA, P/N 440500SEISMICKIT for the 50kVA, P/N 440800SEISMICKIT for the 80/100kVA).
This kit enables the UPS system to conform to the OSHPD seismic certification requirements. See the
4400 Seismic Kit Installation Instructions, P/N 94016, for details.
Anchorage Bolts
Install the anchor bolts to secure the UPS on the floor. See Figure 7.3 for anchor bolt installation detail.
Use 5/8" (16 mm) diameter anchor bolts. There are 0.7" (17.9 mm) diameter holes provided in the UPS
base. See Figure 7.3 and 7.5 for the hole locations and dimensions.
4400 Series UPS Battery Cabinet Installation and Operation Manual – 69445-005
80/100kVA
Skids
Anchor Bolt
FIGURE 7.3 50-100KVA BC ANCHOR BOLT INSTALLATION DETAIL
4 bolt holes
4 x 5/8 in (16 mm) diam-
(Side View)
eter bolt holes
17