To perform the Fill Regulator setup, turn off the conveyor and position a known good container under the test
head. Press ACTIVATE TEST bar. Minimum and Maximum readings are taken and displayed. The Fill Pressure is
then registered below and a pass/fail message will appear in green or red text. This screen shows that the Fill
Pressure reading falls within acceptable parameters. To exit, press: EXIT AND RESTORE: (). Exiting will return
you to the HOME screen. Pressing the ( ) button help utility prompts this series of help screens to appear.
Press: ACTIVATE TEST.
Repeat and re-adjust FILL
pressure until test settings
fall within acceptable limits.
Green "settings are OK"
message appears; the NEXT
button will appear at bottom
right. Press NEXT to
continue.
ALPS SC LINEAR QUICK-START GUIDE
15
REV00 © 02/12/2014
GUIDED SETUP
Locking Rings
The needle will fall within
the green zone
(Within the MIN/MAX
parameters you set).
Note: MIN/MAX values are
standard default values and
cannot be changed.
Continue to Reporting
Times screen

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SC Linear Leak Tester and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Table of Contents