Initial commissioning
Reference to external appli-
ances
A reference to external hardware ap-
pears.
Confirm with the
Before initial commissioning, connect
the XCI box or slide a communication
module into the slot on the back of the
washing machine. The washing ma-
chine must be disconnected from the
power supply. Then start the commis-
sioning process.
Setting the display brightness
You will be asked to select the bright-
ness of the display.
Display brightness
Darker
Touch the segment bars until you
reach the required level of brightness.
The selected brightness level will be
highlighted in orange.
Confirm with OK.
The display will change to the next set-
ting.
18
OK
sensor control.
Brighter
Setting the date
Date
September
August
July
June
May
Place your finger on the value that
you want to change and move your
finger in the direction you want.
Once all values have been selected,
confirm with the OK sensor control.
The display will change to the next set-
ting.
Confirming the time request
The following question appears in the
display:
Remove the clock display?
Touch the
If you select
OK
the
Clock display
If you select
to the
Clock display
25
24
23
22
21
Yes
or
No
sensor control.
Yes
, the system will skip
setting.
No
, the display will switch
setting.
2021
2020
2019
2018
2017
OK