6 General commissioning steps

6.1 Preparing 'Station' for commissioning

Building Technologies
Fire Safety
The following chapter contains general commissioning steps that are referred to in
several chapters.
1. Connect the cables for the detector lines and the periphery devices.
2. Connect the power supply (mains and batteries).
The 'Station' starts and reads in the internal hardware.
During start-up, the 'AVERIA' LED flashes and the display shows the
progress.
During start-up, the firmware version F-FXS7211 is displayed.
3. Wait until the display indicates the selection of the BDV.
4. Press the 'Install' softkey and confirm with the 'Yes' softkey.
The 'Station' restarts.
During this process, the 'AVERIA' LED flashes and the display shows the
progress.
5. Wait until only the green 'Sistema Servicio' LED lights up, the display shows
the normal condition and the 'Station' can be operated.
6. Press <MENU> and select the 'Login/logout' menu item.
You are prompted to enter a PIN.
7. Enter the PIN and confirm with <ok>.
The 'User successfully logged in' message is displayed.
The main menu is shown on the display.
8. Check the firmware of the 'Station' to ensure that it is up to date. To do this
select the 'Topology' > 'Hardware tree' > 'Station' > 'More Options' > 'Show
details' menu items.
The 'Station' version and configuration data are displayed.
9. Update the firmware if necessary.
10. Enter the date and time. To do this, select the 'Settings/administration' >
'System commands' > 'Set system time' menu items.
Additional messages may be displayed depending on the configuration of the
'Station'.