To commission the units, the following working steps must be carried out:
Prerequisite is the correct mounting and correct electrical installation and, in the
case of wireless products, correctly working radio connections to all required
auxiliary units
Make all plant-specific settings. Pay special attention to menu "Configuration".
For that purpose, the relevant operating level is to be selected as follows:
– Press the OK button on the room unit to switch to programming.
– Press the Info button for at least 3 seconds and select operating level
"Commissioning" with the setting knob. Then, press the OK button.
Make the function check as described below
Reset the attenuated outside temperature (Menu "Diagnostics of consumers",
operating line "Outside temp attenuated" (8703))
To facilitate commissioning and fault tracing, the controller can be used to make
input and output tests. With these tests, the controller's inputs and outputs can be
checked. For testing, switch to menu "Input / output test" and work through all
available setting lines.
The current operating state can be checked on menu "State".
For detailed diagnostics of the plant, check menus "Diagnostics heat generation"
and "Diagnostics consumers".
4.1

Basic unit RVS43.345

LED off:
No power
LED on
Ready to operate
LED flashes
Local errors
User manual RVS43.345
Commissioning
LPB
LED