VERSION 11/2018
7
OPERATION
7.1
TRAINING THE OPERATING PERSONNEL
The operating personnel must be qualified to operate the entire system.
The operating personnel must be familiar with the potential risks associated with
improper behavior as well as the necessary protective devices and measures.
Before work commences, the operating personnel must receive appropriate system
training.
7.2
EMERGENCY STOP
In the case of unforeseen occurrences:
– Immediately close the air cut-off valve (4).
ZIP 52 Finishing: An air cut-off valve is installed.
ZIP 52 PF Eco-Finishing: An air cut-off valve must be provided by the user.
– Open the return valve (5) and/or the delivery devices (valves or guns).
7.3
TASKS
Ensure that:
commissioning is carried out in accordance with Chapter 6.7.
1. Visual check:
personal safety equipment, grounding and all devices
ready to use.
2. Secure spray gun and insert nozzle into the spray gun.
3. Slowly open the shut-off valve (4).
4. The pump supplies the product (8) while the spray gun
(9) is open.
5. Set the air pressure to 1–1.5 bar with the pump pressure
regulator (1) and the product pressure regulator (2, for
ZIP 52 Finishing), in order to reach the desired product
amount and/or the desired product pressure.
6. Set the atomizing air pressure regulator (3) to 1.5–2 bar.
7. Start work process.
ORDER NUMBER DOC 2332848
Zip 52 Finishing
9
2
1
8
closed
open
6
5
4
7
3
5
9
6
7
3
1
8
B_06949
29