5 . 1. Po wer sup ply
The electrical power supply must be made by a quali-
fi ed person and must be registered by the local elec-
tricity company. The executive electrical company, is
responsible for the standard-compliant connection
to the electrical installation and the applied safety
measure. Before commissioning all clamps must be
controlled and if necessary they must be retighten.
For electrical details please see the relevant wiring
diagram.
When working on the heat pump, please
be sure that the device is tensionless.
The main supply voltage at the terminals of the heat
pump must be 400 V ± 10%. The dimensions of the
connecting cables must be checked by the executive
electrical company.
A fault-current circuit breaker for the heat pump is not
required. The connection to the protective measure
„protective multiple earthing" is suffi cient. If never-
theless the protective measure „fault-current circuit
breakers", dispatched by the executive electric com-
pany, a separate fault-current circuit breaker for the
heat pump is recommended. This must be designed
as an all current sensitive Type B (IΔN ≥ 30mA). The
specifi ed FI-types related to the heat pump excluding
externally connected components (see Installation
instructions, data sheets).
For the main current circuit as a result of the occur-
ring starting currents, circuit breakers with a tripping
characteristic curve type „C" or „K" must be used.
For the control circuit and the optional electric auxilia-
ry heater, circuit breakers with a tripping characteristic
type „B" or „Z" are suffi cient.
The electrical connection- and supply cables must be
designed as copper cables.
(C) IDM ENERGIESYSTEME GMBH
5. 2 . E MC c o mpa t ib il i t y
For the TERRA SWM, separate cable entries for the
main power supply and for the sensors have been
designed to avoid problems in the fi eld of Electro-
Magnetic Compatibility.
It is especially in the area of responsibility of the elec-
trical company to avoid possible coupling paths when
creating the electrical installation.
EMC-faults can have different effects:
- Short-term measurement faults
- Permanent measurement faults
- Short-term interruption in data connections
- Permanent interruption in data connections
- Data losses
- Damage to equipment
Control of the
groundwater pump
3N~400 V / 50 Hz
1~230 V / 50 Hz
Recommendation: Install
matching Motor protection
switch
Installation instructions TERRA SWM

5. Electrical assembly

installing the electrics
or
Main power supply
3N~400 V / 50 Hz
Control current
230V / 50 Hz
25

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Terra swm 3-13 series

Table of Contents