Special Installation Instructions - ProMinent delta General Operating Instructions

Solenoid metering pumps
Table of Contents

Advertisement

Fig. 19

3.6 Special installation instructions

With high suction-side pressure 1
P_MAZ_0013_SW
Fig. 20
With high suction-side pressure 2
P_MAZ_0014_SW
Fig. 21
With high suction-side pressure 3
P_MAZ_0015_SW
Fig. 22
With high suction-side pressure 1
P_MAZ_0016_SW
Fig. 23
Position the end of the discharge line higher than the fluid level in the
n
storage tank to avoid overstraining.
Position the outlet of the discharge line higher than the fluid level in
n
the storage tank to avoid overstraining.
Install an adjustable back pressure valve in the discharge line and
n
install a shut-off valve in the suction line, which has to be closed when
the pump is at a standstill (preferably a solenoid valve).
If the system is primed from lines with fluctuating pressure, use a
n
hopper with a float valve to ensure a regular discharge flow.
Installation, hydraulic
15