Electrical Installation

4.9 Installation Check List

Before completing installation of the unit, inspect the entire installation as detailed in Table 4.3. Check and mark the items
when completed.
Inspect for
Description
Auxiliary equipment
Look for auxiliary equipment, switches, disconnects, or input fuses/circuit breakers, which may reside on
the input power side of the adjustable frequency drive or output side to the motor. Ensure that they are
ready for full-speed operation.
Check the function and installation of any sensors used for feedback to the adjustable frequency drive.
Remove any power factor correction capacitors on the motor(s).
Adjust any power factor correction capacitors on the line power side and ensure that they are dampened.
Cable routing
Ensure that the motor wiring and control wiring are separated, shielded, or in three separate metallic
conduits for high-frequency interference isolation.
Control wiring
Check for broken or damaged wires and loose connections.
Check that the control wiring is isolated from power and motor wiring for noise immunity.
Check the voltage source of the signals, if necessary.
The use of shielded cable or twisted pair is recommended. Ensure that the shield is terminated correctly.
Cooling clearance
Ensure the top and bottom clearance is adequate to ensure proper air flow for cooling, see
chapter 3.3 Mounting.
Ambient conditions
Check that requirements for ambient conditions are met.
Fusing and circuit
Check for proper fusing or circuit breakers.
breakers
Check that all fuses are inserted firmly and are in operational condition and that all circuit breakers are in
the open position.
Grounding
Check for sufficient ground connections and ensure the those are tight and free of oxidation.
Grounding to conduit, or mounting the back panel to a metal surface, is not a suitable grounding.
Input and output
Check for loose connections.
power wiring
Check that the motor and line cables are in separate conduit or separated shielded cables.
Panel interior
Inspect to ensure that the unit interior is free of dirt, metal chips, moisture, and corrosion.
Check that the unit is mounted on an unpainted, metal surface.
Switches
Ensure that all switch and disconnect settings are in the proper positions.
Vibration
Check that the unit is mounted solidly, or that shock mounts are used, as necessary.
Check for an unusual amount of vibration.
Table 4.3 Installation Check List
CAUTION
POTENTIAL HAZARD IN THE EVENT OF INTERNAL FAILURE
Risk of personal injury if the adjustable frequency drive is not properly closed.
Before applying power, ensure all safety covers are in place and securely fastened.
MG34U422
Instruction Manual
Danfoss A/S © 06/2015 All rights reserved.
4
4
35

Advertisement