Electrical Installation

4.9 Installation Check List

Before completing installation of the unit, inspect the entire installation as detailed in Table 4.5. Check and mark the items
when completed.
Inspect for
Auxiliary equipment
4
4
Cable routing
Control wiring
Cooling clearance
Ambient conditions
Fusing and circuit
breakers
Grounding
Input and output
power wiring
Panel interior
Switches
Vibration
Table 4.5 Installation Check List
CAUTION
POTENTIAL HAZARD IN THE EVENT OF INTERNAL FAILURE!
Risk of personal injury when the frequency converter is not properly closed. Before applying power, ensure all safety
covers are in place and securely fastened.
20
®
VLT
Description
Look for auxiliary equipment, switches, disconnects, or input fuses/circuit breakers that may reside on the
input power side of the frequency converter or output side to the motor. Ensure that they are ready for
full-speed operation
Check function and installation of any sensors used for feedback to the frequency converter
Remove any power factor correction caps on motor(s)
Adjust any power factor correction caps on the mains side and ensure that they are dampened
Ensure that motor wiring and control wiring are separated or screened or in 3 separate metallic conduits
for high-frequency interference isolation
Check for broken or damaged wires and loose connections
Check that control wiring is isolated from power and motor wiring for noise immunity
Check the voltage source of the signals, if necessary
The use of shielded cable or twisted pair is recommended. Ensure that the shield is terminated correctly
Measure that top and bottom clearance is adequate to ensure proper air flow for cooling, see
3.3 Mounting
Check that requirements for ambient conditions are met
Check for proper fusing or circuit breakers
Check that all fuses are inserted firmly and are in operational condition and that all circuit breakers are in
the open position
Check for good ground connections that are tight and free of oxidation
Grounding to conduit, or mounting the back panel to a metal surface, is not a suitable grounding
Check for loose connections
Check that motor and mains are in separate conduit or separated screened cables
Inspect that the unit interior is free of dirt, metal chips, moisture, and corrosion
Check that the unit is mounted on an unpainted, metal surface
Ensure that all switch and disconnect settings are in the proper positions
Check that the unit is mounted solidly, or that shock mounts are used, as necessary
Check for an unusual amount of vibration
HVAC Drive Operating Instructions