Starting and transferring a project
Note
When restarting the system, a project may already be loaded on the HMI device. The project
will then start either following a delay (whose duration can be adjusted) or when you press
the "Start" button.
When the project starts, the following dialog boxes will appear:
• "Establishing secure connection"
• "Testing enabling button"
If you want to transfer another project, for example, proceed as follows:
• Close the project and restart the HMI device.
• If necessary, parameterize the required data channel.
• Select "Transfer" to start the transfer.
Function test
Check whether the HMI device is fully functional. The HMI device is fully functional when one
of the following states is indicated after switching on:
● The "Transfer" dialog is displayed.
● The Loader appears
● The "Test enabling button" dialog box appears.
Switching off the HMI device
To switch the HMI device off, press the ON/OFF button on the HMI device for at least 4
seconds.
If the project has been started, the "Confirm removal" dialog box appears following a prompt.
1. Press one of the enabling buttons to confirm the dialog box.
See also
Inserting batteries for the first time (Page 85)
Mobile Panel 277F IWLAN
Operating Instructions, 12/2007, A5E01003940-01
The HMI device is removed.
The current project is terminated.
The HMI device switches off.
Installation and connection