1. Installation

1.1 General

All staff concerned must acquaint themselves with these
instructions before beginning any work on the unit. Any
damages to the unit or parts of it due to improper han-
dling or misuse by the purchaser or the fitter cannot be
considered subject to guarantee if these instructions have
not been followed correctly.
The product identification plates are located on the
inspection side of the air handling unit and inside the
electric equipment cubicle of the unit. Refer to the particu-
lars on the product identification plate when you contact
Swegon.
The air handling unit is supplied in packaged condition.
Possible ordered accessories are supplied in separate pack-
aging with the unit.
Remove the air handling unit's protective plastic foil pack-
aging when you have completed the installation.

1.2 Transport within the site

Before removing the transport pallet/transport cradle, if
used, determine whether a forklift truck or a pallet trans-
porter will be used for further transporting the unit within
the site to the spot where it will be installed.

1.3 Parts packed together with the unit

Individually packaged components such as the hand-held
micro terminal, decorative fittings, commissioning plates,
bolts, supply air sensor and document pocket are inside
the air handling unit when it is delivered.

1.3.1 Hand-held micro terminal

The hand-held micro terminal is equipped a 3 m long
cable and a quick-fit connector. For particulars of the elec-
trical connections, see 1.15. A holder for wall-mounting
is supplied with the hand-held micro terminal. The holder
can be secured to the outside of the air handling unit
(does not apply to the outdoor units) or another appropri-
ate place. An extension cable (8 metres long) is available
as an accessory.

1.3.2 Supply air sensor

The sensor is equipped with a 10 m long cable and a
quick-fit connector. For particulars regarding installation,
see 1.12. For particulars of the electrical connections, see
1.15.

1.3.3 Document pocket

Secure the document pocket to the exterior of the air
handling unit or another appropriate place.

1.4 Location

The air handling unit must be mounted horizontally on a
flat and firm supporting surface and this surface must be
constructed in a way enabling it to support the weight of
the unit.
Swegon reserves the right to alter specifications.
When installing the air handling unit and connecting pipe-
work and electric cables, make sure that adequate free
space is provided for opening the inspection doors and
covers and withdrawing functional sections, such as filter
cassettes and fan assemblies, clear of the unit casing.
Inspection space required
A clear space of 1,000 mm should be provided in front of
the unit for opening the inspection doors.

1.5 Method of delivery

1.5.1 GOLD RX

The GOLD RX 120 is normally supplied in five separate
sections: two fan sections, two filter sections and one
heat exchanger section.
The heat exchanger section can also be supplied split into
two casing sections and rotor, in which case the rotor is
supplied tilted in a transport cradle (transport height =
2,930 mm, minimum transport width = 2,350 mm). See
Section 1.7 for installation particulars.
For other dimensions and weights, see Section 2.1.
Heat exchanger section supplied as a separate unit
3440
3440
1070
Heat exchanger section, supplied split
1070
into two casing sections and rotor
Rotor, Ø 3150
1868
1868
1070
1170
1070
1170

1.5.2 GOLD CX

The GOLD CX 120 is supplied as six separate units:
Two fan sections, two filter sections and two coil heat
exchanger sections.
For dimensions and weights, see Section 2.2.