Install a lightning protector at the input end of the power supply to enhance lightning protection
•
capability. For how to install a lightning protector, see
power strip with lightning
Rack installation
Reserve at least 1 m (3.28 ft) of clearance between the rack and walls or other UTM devices.
•
Reserve at least 10 cm (3.94 in) of clearance at the air inlet and exhaust vents for ventilation.
•
The equipment room is at least 3 m (9.84 ft) high and an air conditioner is installed.
•
Power supply
Make sure the power source of the installation site is steady and can satisfy the input requirements of
the power modules and parameters such as rated voltage. For power module specifications, see
input."
Installation tools
The tools in the table may be used for installing the UTM device. Prepare them yourself.
Flat-blade
screwdriver
RJ-45 crimping
pliers
Accessories
Console cable (supplied
with UTM device)
protection."
Phillips screwdriver
Needle-nose pliers
Marker
Multimeter
Grounding cable
(supplied with UTM
device)
"Connecting the AC power supply to a
Wire-stripping
pliers
Network cable
tester
U200-A and U200-M
front mounting brackets
(supplied with UTM
device)
11
"Power
Diagonal pliers
Hot air blowing
gun
U200-S mounting
brackets (supplied with
UTM device)
Need help?
Do you have a question about the SecPath U200 Series and is the answer not in the manual?