Specific maintenance work

Fig.65
Replacing the ionisation/ignition
electrode
3
2
1
123157 - v.12 - 07022018
Perform the specific maintenance work if this proves to be necessary fol­
lowing the standard inspection and maintenance work. To conduct the
specific maintenance work:
10.4.1
The ionisation/ignition electrode must be replaced if:
4
AD-0000088-01

Replacing the ionisation/ignition electrode

The ionisation current is < 4 µA.
The electrode is damaged or worn.
The electrode is included in the service kit.
1. Remove the plug of the electrode from the ignition transformer.
Important
The ignition cable is fixed to the electrode and therefore may not
be removed.
2. Remove the two screws.
3. Remove the entire component.
4. Fit the new ionisation/ignition electrode.
5. Reassemble the unit in the reverse order.