Commissioning

7.1

General

7.2

Gas circuit

Fig.37
Gas valve unit measuring points
C
7.3

Hydraulic circuit

7.4

Electrical connections

7.5

Commissioning procedure

123157 - v.12 - 07022018
Follow the steps set out in the paragraphs below to put the boiler into op­
eration.
1. Open the main gas tap.
2. Open the boiler gas tap.
3. Unscrew the two screws located under the front housing by a quar­
ter turn and remove the front housing.
4. Tilt the instrument box forwards by opening the clips on the sides.
5. Check the gas inlet pressure at the measuring point C on the gas
valve unit.
C
AD-0000066-01
6. Vent the gas supply pipe by unscrewing the measuring point on the
gas valve unit.
7. Tighten the measuring point again when the pipe has been fully ven­
ted.
8. Check all connections for gas tightness. The test pressure may be a
maximum of 60 mbar.
1. Check the siphon; it should be fully filled with clean water.
2. Check the water-side connections for tightness.
1. Check the electrical connections.
1. Tilt the instrument box upwards again and fasten it using the clips lo­
cated on the sides.
2. Open the main gas tap.
Warning
Do not put the boiler into operation if the supplied gas is not in ac­
cordance with the approved gas types.
Warning
Ensure that the boiler is disconnected from the power supply.
Warning
The gas pressure measured on measurement point C is the gas
inlet pressure at the boiler connection point reduced by the re­
sistance of the internal gas pipe. See Technical data, page 13
For authorised gas pressures, see: Unit categories, page 12
Warning
Initial commissioning must be done by a qualified professional.
If adapting to another gas type i.e. propane, the gas valve unit
must be adjusted before switching on the boiler.
See
Adjusting to a different gas type, page 44
Important
On first firing the boiler, a smell may be present for a short period.
7 Commissioning
43