• If there is any fault or if the equipment is not working properly,
de-activate the equipment and do not attempt to repair it or
tamper with it directly. Contact only qualified personnel.
• Any product repairs must only be carried out by BALTUR
authorised assistance centres or by its local distributor using
only original spare parts.
• The manufacturer and/or its local distributor are not liable for
any accident or damage caused by unauthorised changes of
the product and by failure to follow the rules described in the
manual.
SAFETY WARNINGS FOR INSTALLATION
• The equipment must be installed in a well-ventilated suitable
room in compliance with the laws and regulations in force.
• Ventilation grille section and installation room aeration openings
must not be obstructed or reduced.
• The installation room must NOT have the risk of explosion and/
or fire.
• Before installing the equipment we recommend to carefully
clean the interior area of all fuel supply system pipes.
• Before connecting the equipment check that the details on the
plate correspond to those of the utility supplies (electricity, gas,
light oil or other fuel).
• Make sure the burner is firmly fixed to heat generator according
to manufacturer instructions.
• Connect to the source of energy according to state-of-the-art
standards as described in the explanatory diagrams and in
compliance with the regulatory and law requirements in force at
the moment of installation.
• Check that the fume disposal system is NOT obstructed.
• If it is decided not to use the burner any more, the following
procedures must be performed by qualified technicians:
- Switch off the electrical supply by disconnecting the power
cable from the main switch.
- Cut off the fuel supply using the shut-off valve and remove
the control wheels from their position.
- Render harmless any potentially dangerous parts.
WARNINGS FOR START UP, TEST, USE AND
MAINTENANCE
• Start up, test and maintenance of the equipment must only be
carried out by qualified technicians, in compliance with current
regulations.
• Once the burner is fixed to the heat generator, make sure
that the generated flame does not come out of any slot during
testing.
• Check equipment fuel supply pipe seal.
• Check that fuel flow rate equals the power required to the
burner.
• Set the burner fuel capacity to the power required by the heat
generator.
• Fuel supply pressure must be within the values indicated on the
plate on the burner and/or manual
• The fuel supply system is suitably sized for the flow required
by the burner and that it has all the safety and control devices
required by current standards.
• Before starting up the burner, and at least once a year, have
qualified technicians perform the following operations:
- Set the burner fuel capacity to the power required by the
heat generator.
- Check combustion and adjust combustion and/or fuel
air flow to optimize combustion and reduce emissions in
accordance with the law in force.
- Check the adjustment and safety devices are working
properly.
- Check the efficiency of the combustion products exhaust
duct.
- Check seal in the fuel supply pipe internal and external
section.
- At the end of the adjustment procedures, check that all
the locking devices of mechanical securing systems are
properly tightened.
- Make sure that the use and maintenance manual of the
burner is available.
• If the burner repeatedly stops in lock-out, do not keep trying to
manually reset it but call a qualified technician.
• If you decide not to use the burner for a while, close the valve or
valves that supply the fuel.
4 / 38
0006081053_201805

Hide quick links:

Advertisement

Chapters

Table of Contents
loading

This manual is also suitable for:

Tbl 85pTbl 85p dacaTbl 105pTbl 260pTbl 130pTbl 105p daca ... Show all

Table of Contents