G. Position posts
Position the columns upright on the installation layout. Position the offside
column parallel to the power side column at the approximate overall width
(1371/2"). Install the overhead cross beam. Do not drill holes for anchor bolts
until overhead cross beam has been installed.
See Fig. 23
Drill the anchor holes to the depth
of the length of the anchor bolts
4"
Fig. 21
Fig. 22
Install the anchor bolts. Check the posts for plumb with level bar, and adjust
with the horseshoe shims if the columns are not plumb. Do not tighten the
anchor bolts.
Installation Steps