Installation
Voltage Check Procedure
Always check both AC and DC voltages during initial setup of the node.
Follow these steps to check AC and DC voltages.
1 Use a true-rms DVM to check for 45 to 90 V AC input voltage at the AC test point on the power supply
module.
2 Check for the various DC output voltages (+24.5, +8.5, -6.0, and +5.5) of the power supply at the DC test
points on the power supply module.
3 Verify that the LED on the OIB is on.
4 Carefully close the housing lid. See
Opening and Closing the Housing, on page