Node Powering Procedure

Node Powering Procedure
Follow these steps to apply power.
1 Determine which of the RF cables carry 45 to 90 V AC input power.
2 Install shunts in the locations that correspond to the AC-powered RF ports. Each port's shunt is located
on the RF amplifier module near the port as shown in the following illustration.
Shunts are available with both red and black tops. Use red to indicate that power is applied to that port.
Note
Use black to indicate that input power is not applied.
3 If desired, remove shunts to block AC power at the individual ports.
4 The next step depends on the power path, as follows:
5 Continue to
Cisco GS7000 Super High Output Intelligent Node Installation and Operation Guide
30
IF...
power will pass from left side of housing (Ports 1,
2, and 3) to right side of housing (Ports 4, 5, and 6)
power is to be blocked between left side of housing
(Ports 1, 2, and 3) and right side of housing (Ports
4, 5 and 6)
Ports 1, 2, and 3 are powered from one source and
Ports 4, 5 and 6 are powered from another source
Voltage Check Procedure, on page
THEN...
ensure that the AC segmentable shunt is installed.
ensure that the AC segmentable shunt is removed.
ensure that the AC segmentable shunt is removed.