COMMISSIONING
10.4 FINAL ACTIVITIES
10.4.1 CLOSING THE BOILER DOOR AND THE
CONTROL PANEL
B Close the boiler door and lock the fastener by turning
the vent screw through ¼ rotation in a clockwise
direction.
Fig. 95
Closing the boiler door
B Push on the control panel to close it.
Fig. 96
Closing the control panel
58
10.4.2 HANDING OVER
After completing the installation and commissioning of
the system the installer should hand over to the end user
by the following actions.
B Hand over all relevant documentation to the end user
and explain his/her responsibilities under the relevant
national and regional regulations.
B Explain and demonstrate the starting and shutting
down procedures.
6 720 648 726-095.1TD
6 720 648 726-044.1TD
NOTE:
B During initial start-up and annual
servicing, make sure that all control,
regulating and safety devices are in full
working order and, if applicable, check
for correct adjustment.
B Always keep the user manual and
installation and servicing instructions by
the boiler.
6 720 648 726 (2011/07)